White Oak Semiconductor Plant 1 & 2

buildings

Power & Energy

USA

Virginia and South Carolina Divisions

For this project, Tindall helped set a record project completion schedule of just over 11 months from the start of construction to the first production – the fastest ever achieved at that time. Three of Tindall’s production facilities supplied nearly 1,500 pieces of precast to support erecting the structure in under two months. Additionally within this timeframe, Tindall’s engineering team was able to conceptualize and design a member to span over the 90,000-square-foot clean room, which consisted of two 128-foot bays, by working closely with the form fabricator to support this extremely fast-track schedule.

Owner

White Oak Semiconductor

Architect

IDC

Contractor

DPR and Austin Commercial

Location

Sandston, VA

Petrochemical Precast at Its Finest.

Tindall provided the engineering expertise needed to allow parallel development of the structure and the overall process by working as part of the design team, taking part in weekly project review meetings, and facilitating close coordination of disciplines. This guaranteed a quick delivery, which is a significant competitive advantage in the global semiconductor market. Exceeding expectations at every turn with the first plant structure, Tindall was awarded the contract for a second structure very early in the process when the decision was made to expand the facility.

Tindall provided a clear 128-foot roof span supporting sensitive equipment over the clean room with minimal deflection. Operating floors that spanned in excess of 100 feet and carried uniform loads of up to 200 psf were accommodated with the same five-foot deep horizontal member. For the vibration sensitive process floors, Tindall provided a shallower system consisting of double tees supported by pocketed beams, with the stems grouted into the pockets, and the entire area covered with a composite reinforced topping.

More Project Information

Specifications
  • Project completed in just over 11 months
  • Supplied nearly 1,500 pieces of precast
  • Conceptualized and designed a member to span over the 90,000-sq. ft. clean room
Components
  • Roof span
  • Double tees
  • Pocketed beams

“From the high quality of your designs, drawings, products and field work to the execution of accurate administrative details — every step and process was completed and delivered in a timely and professional fashion.”

JOHN CARTWRIGHT | AUSTIN COMMERCIAL